How Long Does It Take to Build a Custom Inground Pool in NC?

It’s one of the first questions we hear from homeowners who are ready to move forward: “How long is this actually going to take?” It’s a fair question — you’re making a significant investment, and you want to know when you’ll be swimming. The honest answer for a custom concrete inground pool in coastal North Carolina is 8 to 12 weeks from the start of construction to your first swim. Here’s what that timeline looks like in practice, and what can affect it.

First, Why Does It Take That Long?

If you’ve been comparing options and researching concrete vs fiberglass pools, you may have noticed that fiberglass installations are sometimes advertised as faster. That’s true — a fiberglass shell can drop into a hole in a matter of days. But custom concrete pools are built entirely on-site, layer by layer, which takes more time and delivers a far superior result. There’s no compromising on shape, size, or features, and the finished product is built to last a lifetime.

As one of the leading pool contractors in Brunswick, New Hanover, and Pender County, Smart Pools manages the entire process from design to first swim — so let’s walk through exactly where those weeks go.

Before we start: Permitting

Before any dirt moves, your permits need to be approved. Smart Pools handles all permitting on your behalf, but county review timelines are outside our control. In Brunswick and New Hanover Counties, permit approval typically takes one to two weeks depending on workload.

If your property is waterfront a CAMA permit will need to be approved. CAMA adds 2-4 weeks to the permitting as it is a much more rigorous process. Smart Pools is well versed in CAMA permitting.

Weeks 1-2: Site Preparation, Excavation, and Form and Steel

During the permitting process we will call for utility location services for your property. Once necessary permits are approved and utilities are marked, our in-house crews will being prepping site access, laying out the pool, confirming all details of the layout with you, and then begin excavation.

As an experienced pool builder near me for coastal NC homeowners, our crews know how to work efficiently in sandy coastal soils and manage the higher water tables common in this region; conditions that can slow down less experienced Wilmington pool companies. A dewatering system is often needed to reduce the water table between the time of excavation and concrete installation. Dewatering systems can include one well point or many. Ground water control is so important to pool construction as ground water can negatively affect preparation for and quality of the concrete shell. Our in-house crews are experts at ground water control.

Once the hole is excavated, our team installs the framing and steel rebar; the structural backbone of your pool. This is the phase that best illustrates why in-ground pool homeowners in Wilmington, Ocean Isle Beach, Hampstead, Leland, Wrightsville Beach, Oak Island, and surrounding areas prefer concrete over other materials. The rebar is custom-bent to match your exact pool design, meaning no compromises on curves, depth transitions, or custom features like tanning ledges or attached spas.

Weeks 2–4: Gunite & Shell Construction

After a steel bonding inspection, we apply gunite — a pneumatically sprayed concrete mix — over the framework to form the shell. The gunite then needs time to cure properly before the next phase begins. Rushing this step is never an option; proper curing is what gives your pool its long-term structural integrity.

Weeks 4–6: Plumbing, Electrical & Equipment

With the shell cured or while it cures, our in-house crews complete long plumbing, including and our trusted electrical subcontractors install conduit. Pool equipment — pumps, filters, heaters, automation systems, and lighting — is set and wired during this phase. Each stage requires its own inspection sign-off before work can proceed.

Smart Pools installs the most state of the art app-controlled automation systems as standard on most builds, something that distinguishes a true high-end pool builder from a basic contractor. These systems let you control your pool’s temperature, lighting, energy efficiency, and water features from your phone.

Weeks 6–9: Coping, Tile, Decking & Surrounds

This is the phase where your backyard starts to look like the design you approved. Coping is installed around the pool’s perimeter, tile around the waterline, and then your chosen deck material — whether that’s travertine pavers, composite decking, broom finished concrete, or concrete with spray deck applied. If your project includes an outdoor kitchen, pergola, game area, or turf… those elements are coordinated during this phase as well.

For homeowners who want a truly complete backyard transformation, this is where working with a full-service pool design company NC matters most. Smart Pools coordinates all trades so you’re not managing multiple contractors on your own.

Weeks 9–12: Interior Finish, Fill & Startup

The interior finish — pebble, quartz, or hybrid plaster — is applied and carefully cured. We then begin filling the pool, a process that takes 24 to 48 hours depending on pool size. Water chemistry is balanced from the start, and all equipment is tested and commissioned.

Before we hand over the keys, our team walks you through a complete orientation: how to operate your equipment, how to maintain your water chemistry, and how to get the most out of your automation system. We don’t consider the job finished until you’re fully confident as a pool owner.

What Can Affect the Timeline?

Most Smart Pools projects land in the 8–12 week window, but a few factors can push timelines in either direction:

•       Permit processing times — county workloads vary by season

•       Weather — extended rain delays excavation and concrete work

•       Project complexity — larger pools with multiple water features or full outdoor kitchens take longer

•       Material lead times — specialty coping or tile selections, especially those coming from across an ocean occasionally have longer delivery windows

•       Inspection scheduling — county inspectors set their own availability

One thing that never affects our timeline: shortcuts. As luxury pool builders NC homeowners trust, we don’t skip cure times, rush inspections, or compromise quality to move faster. Every step is done right, the first time.

When Should You Start Planning?

The best time to start your pool project is before in the off season. If you want to be in the water by Memorial Day, you should be breaking ground no later than February — which means your design consultation and permitting process should start in November or December. Spring is our busiest season, and project slots fill up fast.

As a concrete pool builder Wilmington NC homeowners have relied on for years, Smart Pools serves communities across Brunswick, New Hanover, and Pender Counties — from Leland and Southport to Ocean Isle Beach and Hampstead. The earlier you reach out, the more flexibility you’ll have on your start date.

Ready to Get Started?

Contact Smart Pools today to schedule your free design consultation. We’ll walk you through the entire process, give you a realistic project timeline based on your specific lot and design goals, and make sure you know exactly what to expect from day one to first swim.